Every figure on this site traces to a row in data/compute.json with its value, range, unit, as-of date, confidence and source. Figures from Iggy’s source doc were re-checked against the cited sources on 2026-10-20. Where they differ, we log it here instead of quietly changing it.

Discrepancy log

#ItemDoc saysSource saysHow we handle it
D1Colossus 2 in H100e~550,000 GB200/GB300 deployed (~1.4M H100e)State of AI gives the 550,000 GPU count only (no H100e). Epoch (May 2026) says xAI is 'targeting a major expansion of Colossus 2 to around 1.4 million H100e' — i.e. a target, not the deployed figure.Site charts GPU counts; the 1.4M H100e figure is shown only as a flagged note.
D2Parent-company ownership, Q1 2026Google ~5.5M (~31%), Microsoft ~3.3M, Meta ~2.0M, Amazon ~1.5M, Oracle ~1.1M as of Q1 2026Numbers match Epoch's table exactly, but the same page says 'Q1 2026 data is excluded as it was not yet finalized' and its headline uses Q4 2025 (Google 5.0M / 24.8%). Q1 2026 Amazon (1.5M vs 2.5M) and Meta (2.0M vs 2.3M) are lower than Q4 2025, which suggests incomplete preliminary data.Q1 2026 shown as in doc, labeled preliminary, with Q4 2025 values plotted alongside.
D3Google share of global compute~31% of global AI compute31.0% in Epoch's preliminary Q1 2026 row; ~25% (24.8%) at end-2025, which Epoch's text uses ('around a quarter').Both shown.
D4OpenAI future capacityRoughly 30 GW by 2030 through StargateAltman (Oct 28, 2025): ~$1.4T committed ≈ ~30 GW across all partners (AMD, Broadcom, Nvidia, Oracle, …). Stargate itself is the $500B / 10 GW program. No 2030 date in the coverage we found.Shown as '~30 GW total commitments (all partners)'; '2030' flagged as unverified timing.
D5Meta Superintelligence Labs compute~996K in table; '1.00M' in doc chart996,000 (90% CI 606,000–1,638,000)Uses 996,000.
D6Anthropic $517B~14.8 GW / ~$517B in capacity deals over 11 monthsMatches The Information's tally (via DCD/Dealroom summaries; original paywalled). It is a reporter tally, not a company disclosure. Reuters on the IPO prospectus: 'at least $518 billion' over a decade, ~80% non-cancelable.Both figures shown with provenance.
D7Prometheus ~1 GW~1 GWOct 19, 2026 Meta post calls it 'gigawatt-scale' and gives no exact GW; Meta's 2025 statements targeted 1 GW by end-2026.Shown as ~1 GW (announced target).

Couldn’t verify

Sources

  1. Introducing the AI Chip Users Explorer — Epoch AI, 2026-09-09. Checked 2026-10-20.
  2. Data on AI chip users — Epoch AI, 2026-09-09. Checked 2026-10-20.
  3. AI chip users — methodology — Epoch AI, 2026-09-09. Checked 2026-10-20.
  4. Five hyperscalers now own over two-thirds of global AI compute — Epoch AI, 2026-04-14. Checked 2026-10-20.
  5. Frontier labs don't use most AI compute (yet) — Epoch AI (Gradient Updates, opinion), 2026-05-20. Checked 2026-10-20.
  6. Who has the largest GPU cluster in this index? — State of AI Report Compute Index (Nathan Benaich, Air Street Capital), 2026-10-01. Checked 2026-10-20.
  7. Inside Prometheus: Meta's Journey to a Gigawatt-Scale Supercluster — Meta Engineering, 2026-10-19. Checked 2026-10-20.
  8. Why networking infrastructure is critical for AI innovation — Meta Careers blog, 2025. Checked 2026-10-20.
  9. Mark Zuckerberg says Meta is building a 5GW AI data center — TechCrunch, 2025-07-14. Checked 2026-10-20.
  10. How Anthropic Clinched $517 Billion in Compute Deals in 11 Months — The Information (paywalled), 2026-09-06. Checked 2026-10-20.
  11. Anthropic signed $517bn in compute agreements in past 11 months — DatacenterDynamics, 2026-09-07. Checked 2026-10-20.
  12. Anthropic's $518 billion AI buildout hinges largely on deals that cannot be canceled, filing shows — Reuters (via Investing.com), 2026-09-29. Checked 2026-10-20.
  13. Higher usage limits for Claude and a compute deal with SpaceX — Anthropic, 2026-05-06. Checked 2026-10-20.
  14. OpenAI wants to get to $1 trillion a year in infrastructure spend, Altman says — Axios, 2025-10-28. Checked 2026-10-20.
  15. OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites — OpenAI, 2025-09-23. Checked 2026-10-20.
  16. Introducing Muse Wonder and Muse Wonder Full: Frontier Models for Agents — Meta, 2026-10-12. Checked 2026-10-20.
  17. Introducing dots — OpenAI, 2026-09-29. Checked 2026-10-20 (page blocked automated fetch; not independently verified).
  18. Introducing Grok Bot — xAI / SpaceX, 2026-08-11. Checked 2026-10-20.
  19. Claude release notes — Anthropic, 2026. Checked 2026-10-20.
  20. The Gemini app becomes more agentic, delivering proactive, 24/7 help — Google, 2026-05-19. Checked 2026-10-20.
  21. Personalized AI companion app Dot is shutting down — TechCrunch, 2025-09-05. Checked 2026-10-20.

Data

Free sample CSV (compute used by lab). The full data pack is part of the Compute Brief. Epoch AI data is CC BY 4.0 — please credit Epoch AI.